Finish-date range: from the project’s last six finished sprints in its connected source, 10,000 simulated futures give the dates the project is 50%, 80% and 95% likely to finish by, and the chance of meeting the target. It needs at least four finished sprints with completed points. Calculated; no AI.

What-if: change capacity (for example −20% from 1 February) or scope (points added or removed) and compare with the plan. A what-if isn’t saved; raise a change request to change the plan.

  • ServiceNow project status: written from a status report a person submitted — overall health, schedule and the report’s summary, issues and next steps.
  • Azure DevOps comment on a work item, or Jira comment on an issue, written by the project manager.
  1. 1
    Turn on write-back for a source
    An admin opens the project → Connected data → Write-back and enters a separate credential that can write. It’s tested first, encrypted and never shown again. Turn off removes it.
  2. 2
    Propose
    A project manager chooses what to write and proposes it. Nothing is written yet.
  3. 3
    Approve
    Someone with “Approve project decisions” — never the person who proposed it — approves it. TicketResolve writes it, reads it back, and rolls it back at once if what it reads doesn’t match.
  4. 4
    Roll back if needed
    Roll back deletes the status record or comment that was written. Every proposal, approval, write and rollback is kept.
Note:Write-back is off unless an admin turns it on, and each write needs a second person’s approval. The connectors are labelled not production-verified until they’ve run against a live account.
Tips & tricks
  • AI assistants connected to TicketResolve’s MCP server with a read key can ask for programmes, a project’s health and its forecast range (prj_programmes, prj_project_health, prj_forecast). Restricted projects and budgets aren’t included.