Finish-date ranges, what-if and write-back
Finish-date ranges, what-if and write-back
See how likely a market is to finish by its target, try capacity and scope changes, and write approved status and comments back to ServiceNow, Azure DevOps and Jira.
AI Project Manager add-on, $99 per Project Manager seat a month; part of the 7-day free trial Open in TR-AI5 min
Finish-date range: from the project’s last six finished sprints in its connected source, 10,000 simulated futures give the dates the project is 50%, 80% and 95% likely to finish by, and the chance of meeting the target. It needs at least four finished sprints with completed points. Calculated; no AI.
What-if: change capacity (for example −20% from 1 February) or scope (points added or removed) and compare with the plan. A what-if isn’t saved; raise a change request to change the plan.
- ServiceNow project status: written from a status report a person submitted — overall health, schedule and the report’s summary, issues and next steps.
- Azure DevOps comment on a work item, or Jira comment on an issue, written by the project manager.
- 1Turn on write-back for a sourceAn admin opens the project → Connected data → Write-back and enters a separate credential that can write. It’s tested first, encrypted and never shown again. Turn off removes it.
- 2ProposeA project manager chooses what to write and proposes it. Nothing is written yet.
- 3ApproveSomeone with “Approve project decisions” — never the person who proposed it — approves it. TicketResolve writes it, reads it back, and rolls it back at once if what it reads doesn’t match.
- 4Roll back if neededRoll back deletes the status record or comment that was written. Every proposal, approval, write and rollback is kept.
Note:Write-back is off unless an admin turns it on, and each write needs a second person’s approval. The connectors are labelled not production-verified until they’ve run against a live account.
Tips & tricks
- AI assistants connected to TicketResolve’s MCP server with a read key can ask for programmes, a project’s health and its forecast range (prj_programmes, prj_project_health, prj_forecast). Restricted projects and budgets aren’t included.