Tracking dependencies and what you’re waiting on

Tracking dependencies and what you’re waiting on

See which dependencies will move go-live, and everything waiting on the customer or a third party.

Included in every plan Open in TR-AI3 min
  1. 1
    Open Dependencies
    Each dependency shows its owner, the task it blocks, the date it’s needed by and its state: on track, at risk (due within 5 working days) or blocking go-live with the working days it moves go-live.
  2. 2
    Record the promise
    When the owner commits to a date, enter it as Promised for. A promise later than the needed-by date shows immediately as blocking, with the slip.
  3. 3
    Close it with evidence
    Mark done needs a link or a short note.
  4. 4
    Work the queue
    Implementations → Waiting on lists everything open across implementations, grouped by us, the customer or a third party, most urgent first.
Tips & tricks
  • Owners get a daily summary of what’s due, overdue or blocking. Customer and third-party items go to the implementation manager.