Contract deadlines, reminders and renewals

Contract deadlines, reminders and renewals

How notice deadlines are calculated, who is reminded when, acting on reminders, renewal cases and the calendar.

AI VP of Operations add-on Open in TR-AI7 min

Every contract in force shows its critical dates on its page under Deadlines and reminders: expiration, renewal date, the cancellation notice deadline (renews automatically) or renewal notice deadline (renews only if both sides agree), the auto-renewal date and the next payment renewal. The action deadline at the top is the one that decides what has to happen next.

  • Notice periods count full days before the renewal or end date: 31 December with 60 calendar days gives 31 October. Months count back whole months (31 December − 2 months = 31 October; month ends and leap years are handled). Business days skip the working days and holidays in Vendor settings.
  • A deadline that falls on a non-working day shows the working day to act by.
  • Auto-renewal is never assumed. Without a renewal type the deadline is labelled “renewal terms not confirmed” — set it on the contract from the signed copy.

Reminders are planned for the notice deadline and for the end / renewal date — by default 180, 120, 90, 60, 30, 14, 7 and 3 days before and on the day, and 1 and 7 days after the end if nothing was resolved — at the send hour in your time zone. Who is told widens as the date nears: the contract owner (or whoever reminders were reassigned to); from 60 days the department head; from 30 procurement and finance; from 14 legal and leadership; from 7 approvers, for any decision still pending. A missed notice deadline sends one critical alert.

  1. 1
    Acknowledge
    You have seen it; later reminders still come.
  2. 2
    Snooze
    Until a later day — never past the date the reminder is about. When it comes back, everyone it is for is told again.
  3. 3
    Reassign
    Send this and every later reminder for the contract to someone else who can see it.
  4. 4
    Complete
    Say what was done (for example “notice sent on 20 October”). The rest of that deadline’s reminders stop.
  • Deliveries shows, per person, whether the in-app notification was created and whether the e-mail was accepted by the mail service, not sent (and why — their preferences, no address) or failed. Failed e-mail is retried (5, 10, 20, 40 minutes; then the reminder shows Failed).
  • Reminders run on the scheduler every 10 minutes whether or not anyone opens the app, and stop when the contract is no longer in force or its renewal case closes.
  • Restricted contracts are only sent to people allowed to see them; values only to people who may see values.

Renewal cases open automatically at the review window (90 days before the action deadline by default; Open a renewal case does it earlier). Work through the 14 steps — security, compliance, finance, legal and procurement steps are marked by people with that access — then record the decision with its justification and evidence. Someone else with “Approve vendors” approves it or sends it back. Approving renews nothing: Draft the renewal contract creates the next contract, which needs its own approval and signed copy; the case closes with what actually happened (renewed, terminated, expired).

Contract calendar: month, week, list and timeline views of starts, ends, renewal dates, notice deadlines (⚑), renewal decisions due and payment renewals, filtered by vendor, department, owner, category, status and vendor risk.

Tips & tricks
  • Settings → Contract deadlines and reminders: time zone, send hour, working days, holidays, reminder days, escalation steps, who gets missed-deadline alerts, the review window, and extra recipients for contracts above a value or with a given vendor risk.