Starting an implementation and checking the plan fits

Starting an implementation and checking the plan fits

Draft a plan from the accepted sales hand-off and see whether go-live fits the target.

Included in every plan Open in TR-AI4 min
  1. 1
    Find the hand-off
    Implementations → Ready to start lists sales hand-offs delivery has accepted. Click Start implementation. No hand-off? Use Start without a hand-off and enter the requirements, one per line (“must:” for must-haves).
  2. 2
    Give the dates and team size
    Kickoff date, target go-live, the contractual go-live if the contract commits to one, the segment and how many technical consultants will work on it.
  3. 3
    Read the feasibility line
    Green means go-live fits the target, with the working days to spare. Red says how many working days late it is and which chain of tasks sets it. The plan never compresses itself to fit.
  4. 4
    Adjust and re-draft
    Change the dates, segment or number of consultants and click Re-draft. Must-have requirements each have their own task; gaps became risks and decisions; items to verify became early tasks.
Tips & tricks
  • Durations are working days. After three completed implementations, they follow how long your own work actually took.
  • Nothing is created until you accept the plan.