Scheduling, baselines and changes

Scheduling, baselines and changes

Link tasks, find the critical path, baseline the plan and control changes to it.

AI Project Manager add-on, $99 per Project Manager seat a month; part of the 7-day free trial Open in TR-AI4 min
  1. 1
    Link the tasks
    Open a project → Schedule → Dependencies: choose which task comes before which, the type and any lag.
  2. 2
    Read the critical path
    Tasks with no float are on the critical path; if it finishes after the target date, the date shows in red.
  3. 3
    Baseline the plan
    Propose a baseline when the plan is agreed. Someone else approves it; slippage is measured against it from then on.
  4. 4
    Control changes
    Changes → Request a change with its impact on schedule, budget and effort. Someone else decides it; an approved new target date moves the project’s target.
  5. 5
    Track risks and issues
    Risks and issues → record probability and impact, an owner and a response. High risks without a response are flagged.
Tips & tricks
  • Durations come from task dates, else the estimate at 8 hours a day.
  • The forecast at the current rate is an estimate, not a commitment.