Scheduling, baselines and changes
Scheduling, baselines and changes
Link tasks, find the critical path, baseline the plan and control changes to it.
AI Project Manager add-on, $99 per Project Manager seat a month; part of the 7-day free trial Open in TR-AI4 min
- 1Link the tasksOpen a project → Schedule → Dependencies: choose which task comes before which, the type and any lag.
- 2Read the critical pathTasks with no float are on the critical path; if it finishes after the target date, the date shows in red.
- 3Baseline the planPropose a baseline when the plan is agreed. Someone else approves it; slippage is measured against it from then on.
- 4Control changesChanges → Request a change with its impact on schedule, budget and effort. Someone else decides it; an approved new target date moves the project’s target.
- 5Track risks and issuesRisks and issues → record probability and impact, an owner and a response. High risks without a response are flagged.
Tips & tricks
- Durations come from task dates, else the estimate at 8 hours a day.
- The forecast at the current rate is an estimate, not a commitment.