Go/no-go readiness for each market

Go/no-go readiness for each market

See whether a market is ready to go live — from its delivery data and what its customers report to support — and record a go or no-go by named approvers.

AI Project Manager add-on, $99 per Project Manager seat a month; part of the 7-day free trial Open in TR-AI5 min

Each project in a programme can be a market with its own go-live. Its readiness is a list of items: some calculated from its data, some recorded by its project manager. The score is the share of required items met.

  • Schedule isn’t red and Quality isn’t red: from the market’s health (“Not enough data” counts as not met).
  • No open highest-priority defects: from the connected Azure DevOps, Jira or ServiceNow items.
  • Cutover rehearsal done: the milestone you choose, or any milestone named “… rehearsal”.
  • Delivery data read recently: every connected source read within the hours set (24 by default) and none failing.
  • Customer impact within limits: open urgent and high-priority tickets, open problems and known issues, and the share of recent tickets reopened, for the customers in the market’s support scope. With no scope set it’s not met.
  • Manual items you add (training, communications, sign-offs). Marking one met needs evidence — a link or a note.
  1. 1
    Set the support scope
    Open the project → Connected data → Go-live readiness → Support scope. Add the Customer Success accounts, organisations or ticket categories this market serves, and save.
  2. 2
    Choose the rehearsal milestone
    Pick the milestone that stands for the cutover rehearsal.
  3. 3
    Record manual items
    Add what else must be true before go-live and mark each met with evidence, or not applicable.
  4. 4
    Ask for go/no-go
    With “Manage projects”, Ask for go/no-go captures readiness, writes a short rationale from it (every sentence cites the readiness facts) and tells the approvers.
  5. 5
    Decide
    Someone with “Approve project decisions” who isn’t the requester or the market’s project manager decides go or no-go with a reason. A go with items not met needs a waiver with a reason for each. One no-go closes the request; with two approvers set, a go needs both.
Note:Decisions are kept as they were made, with the readiness at that moment, who decided and every waiver. The rationale never recommends go or no-go — the approvers decide. It uses one written AI output from the daily limit; at the limit the request goes ahead without it.
Tips & tricks
  • Admins set the number of approvers and the support limits under Programmes → Go-live readiness.
  • Programmes shows each market’s readiness score and the latest decision.