Delivery Forecasts From Your Own History
“When will it be done?” deserves a better answer than a single date someone guessed in a planning meeting. Engineering Intelligence tracks projects and forecasts them as ranges, 50, 85 and 95 percent dates from your team’s finished work, with every health call explained.

In January, the product team at a B2B SaaS company asks engineering when the new reporting module will be ready. The tech lead, Sven, looks at the backlog (64 items), thinks about how fast the team usually goes, and says: "End of March." Sales hears "31 March" and starts promising it.
By mid-March, 22 items are still open. Two were blocked for three weeks waiting on the data-platform team. Scope grew by 15 items after a customer workshop. Nobody updated the date, because the date had become a commitment the moment Sven said it.
The module ships on 2 May. Two prospects who were promised March have signed with a competitor.
Sven wasn't careless. A single date from memory can't account for normal variation, blocked work or scope growth, and once it's said out loud, nobody wants to change it.
"When will it be done?" deserves a better answer than a single date someone guessed in a planning meeting.
First, the basics
- A project here is a body of work with a goal and a target date, found in your tracker by an epic or parent key, a tracker project or a label.
- A work item is one ticket in Jira, Linear or GitHub.
- Throughput is how many items a team finishes per week.
- A forecast as a range gives several dates with likelihoods. The 50% date is as likely to be beaten as missed; the 85% date is likely; the 95% date is very likely.
- A simulation (here, Monte Carlo) replays the team's past weeks thousands of times in random order to see how long the remaining work could take.
- A milestone is a key point in the project. A dependency is something the project waits for from another team.
- Scope growth is items added after the project started.
- Cycle time is how long one item takes from start to finish. Ageing work has been in progress unusually long.
Why does this matter? Customers, sales and leadership plan around delivery dates. A range based on the team's own history, with honest reasons when a project slips, lets people plan for the likely case and talk early about the risks, instead of discovering them at the deadline.
The problem, in plain terms
- Dates are guessed in meetings.
- A single date hides uncertainty, and becomes a promise.
- Blocked work and dependencies aren't visible until they're late.
- Scope grows quietly.
- "At risk" is an opinion, without reasons.
- Sprint reports hide what was added after the sprint started.
Projects, matched to real work
Add a project with its team, owner, goal and target date, and say how its work is found in your tracker: an epic or parent key, a tracker project, or a label. Work items are read hourly from the Jira, Linear or GitHub tracker you already connected (read-only), or imported from a CSV. Milestones and dependencies on other projects or teams sit alongside.
Forecasts as ranges
We take the team's finished items for each of the last 12 weeks and run 5,000 simulations: pick a past week at random, again and again, until the remaining items are done. The result is three dates (50, 85 and 95 percent), and the basis is printed next to them.
With fewer than four weeks of finished work, there's no forecast. The page says so rather than inventing one.
Health with its reasons
Every project is on track, at risk or off track, and the reasons are always listed:
- the 85 percent date against the target;
- a target already passed;
- overdue milestones;
- dependencies past their needed-by date;
- a fifth of open work blocked;
- scope up a quarter in two weeks;
- nothing finished in two weeks.
A label with no reason is an opinion; a label with reasons is something you can act on.
Sprints, flow and the path to production
- Sprints show what was done, what was added after the start and what was carried over, built from what each sync saw, which we say plainly.
- Flow shows work in progress, blocked and ageing work, weekly throughput and cycle time.
- When pull request titles name the item key, each item can be followed from backlog through review and merge to production, with the median wait at each step.
All calculated, no AI. Names of assignees appear only for people allowed to see individual data.
A worked example, start to finish
Here's the same reporting module, a year later, for its second version.
January, week 1. Sven opens Delivery → Projects and adds Reporting v2: team Insights, owner Sven, goal self-serve report builder, target date 31 March. Its work is matched by the epic key INS-400. Work items are read hourly from Jira.
Week 1. The forecast appears, with its basis printed: "Remaining 58 items; Insights finished 4–9 items a week over the last 12 weeks (median 6); 5,000 simulations."
- 50%: 17 March
- 85%: 7 April
- 95%: 21 April
Health: at risk. Reason: 85% date is 7 days after the target.
Week 1, planning meeting. Instead of saying "end of March", Sven shows the range. Product agrees to move two nice-to-have items to v3. The forecast updates: 85% date 27 March. Health: on track. Sales is told: "Late March is likely; we'll confirm by mid-March."
Week 2. Sven adds a milestone (beta to five customers, 1 March) and a dependency: new aggregation API from Data Platform, needed by 10 February.
Week 6. The aggregation API is late. Health turns at risk, with the reason: dependency "aggregation API" past its needed-by date (10 Feb). Sven escalates to the data-platform lead the same day.
Week 8. After a customer workshop, 14 items are added to INS-400. Health: off track. Reasons: scope up 26% in two weeks; 85% date 14 April, after target. Product decides which of the new items can wait for v3; 9 are moved. The 85% date returns to 2 April.
Week 9. Sprints for Insights show sprint 18: 21 items done, 6 added after the start, 4 carried over, built from what each sync saw. Flow shows three items ageing in review for over a week. The path to production shows the median wait for review is 2.4 days, the longest step. The team agrees a review rotation.
Mid-March. The 85% date is 29 March. Sven confirms "end of March" to sales, with confidence.
30 March. Reporting v2 ships.
Five more real-world scenarios
1. A brand-new team
Situation. A team formed three weeks ago asks for a forecast.
How TR handles it. With fewer than four weeks of finished work, there's no forecast, and the page says so.
2. A project with no tracker connection
Situation. A partner team tracks work in a spreadsheet.
How TR handles it. Import work items as a CSV with key, title, status and created columns.
3. Nothing moving
Situation. A project finishes nothing for two weeks.
How TR handles it. It's flagged with the reason nothing finished in two weeks.
4. Blocked work piling up
Situation. A quarter of a project's open items are blocked.
How TR handles it. It's at risk, with the reason a fifth of open work blocked.
5. Privacy for individuals
Situation. A director without individual access views flow.
How TR handles it. Assignee names appear only for people allowed to see individual data.
Before and after
Before. "End of March" from memory, treated as a promise, and a May delivery that lost two deals.
After. A range from the team's own history with its basis printed, health with reasons, dependencies and scope growth flagged as they happen, and a date confirmed when it's likely.
How to tell it's working
- Dates are communicated as ranges, then confirmed as they firm up.
- Every at-risk or off-track project has a reason people act on.
- Scope changes are decided, not absorbed.
- The longest wait on the path to production shrinks.
Who it's for
- Engineering managers and tech leads asked "when will it be done?"
- Product managers who plan launches.
- Sales and customer success who make commitments to customers.
How it fits with the rest of TicketResolve
This was phase 2 of Engineering Intelligence, after organisation, teams and DORA metrics. Work items come from the tracker connected under Escalation → Hand-offs & engineering. Next came quality, technical debt, architecture and releases, then capacity and budget, the AI Director and reports.
Mistakes to avoid
- Quoting the 50% date as a commitment. Half the time you'll miss it. Use the 85% date.
- Matching projects too broadly. A label shared with other work pulls in the wrong items.
- Ignoring scope growth. Decide what moves, or the date will.
Do it in TicketResolve, step by step
Where: Engineering Leadership → Delivery (/dashboard/engineering-leadership/delivery). You'll need: Jira, Linear or GitHub connected under Escalation → Hand-offs & engineering (or a CSV), and teams set up. Full guide: Projects, forecasts and sprints.
- Bring in work items. Delivery → Work items: with Jira, Linear or GitHub connected, items are read hourly (read-only). Otherwise import a CSV with key, title, status and created columns.
- Add a project. Name it, pick the team and target date, and say how its items are matched: a parent or epic key, a tracker project name or a label.
- Add milestones and dependencies. Open the project to add milestones with due dates and what it's waiting on from another project or team.
- Read the forecast. The 50%, 85% and 95% dates come from 5,000 simulations over the team's weekly finished items in the last 12 weeks. With fewer than 4 weeks of finished work there's no forecast.
- Read the health reasons. On track, at risk or off track always lists why.
- Watch sprints and flow. See what was added after the start, ageing work, and the median wait at each step to production.
How to check it worked: each project shows three forecast dates with their basis, and its health label lists at least one reason.
Frequently asked questions
How is the forecast calculated? 5,000 simulations over the team's weekly finished items in the last 12 weeks.
Why three dates? 50%, 85% and 95% show how likely each date is. The 85% date is a sensible one to plan around.
What if the team is new? With fewer than four weeks of finished work, there's no forecast.
How is a project's work found? By an epic or parent key, a tracker project, or a label.
How often are work items read? Hourly, read-only.
What makes a project at risk or off track? Reasons such as the 85% date after the target, overdue milestones, late dependencies, blocked work, scope growth or no progress.
Is AI used? No. It's all calculated.
Who sees assignee names? Only people allowed to see individual data.
Explore Topics
Written by
Ghulam Shabbir
Content creator and writer sharing insights and stories.


