# Earned Value Without the Spreadsheet

> Two questions sink more projects than any technical risk: is anyone carrying too much, and are we spending faster than we’re delivering? The AI Project Manager covers people and money: allocations across projects with over-capacity weeks flagged, budgets approved by someone else, labour from hours and rates, earned value, and sprints with velocity and a burndown.

Source: https://www.ticketresolve.ai/blog/earned-value-without-the-spreadsheet · Published 2026-11-17 · TicketResolve AI

At a digital agency, a website rebuild for a retail client is "on track" according to the weekly status report. It's month four of six. The project manager, Kofi, reports green because the design and front-end milestones were hit.

Two things nobody can see:

- **Abena**, the agency's only senior back-end developer, is allocated 50% to this project, 40% to an e-commerce integration and 40% to a support retainer. She's been working evenings for six weeks. Each project manager sees only their own allocation.
- **The budget** was £180,000. £148,000 has been spent, mostly on back-end hours at Abena's rate, but only about half the work is done. Nobody has compared spend with progress, because doing it means exporting timesheets, matching them to rates and building a spreadsheet that's out of date the day it's finished.

In month five, Abena resigns, and the finance director discovers the project will finish around £260,000.

Two questions sink more projects than any technical risk: is anyone carrying too much, and are we spending faster than we're delivering?

## First, the basics

- **An allocation** gives a person to a project for a share of their time, such as 50%, between two dates.
- **Capacity** is how much someone can do in a week. **Over capacity** means more than 100% allocated, or more task hours than a working week.
- **A budget** is the planned spend, by category (labour, software, vendors). **A change request** is a formal request to change the budget, scope or schedule.
- **Labour cost** is hours worked times the person's rate.
- **Earned value (EV)** is how much of the budget the completed work is "worth": if 40% of the work is done, EV is 40% of the budget.
- **Planned value (PV)** is how much should have been spent by now, based on time. **Actual cost (AC)** is what's really been spent.
- **CPI** (cost performance index) = EV ÷ AC. Below 1 means work costs more than planned. **SPI** (schedule performance index) = EV ÷ PV. Below 1 means it's behind.
- **Estimate at completion (EAC)** is the forecast final cost if things continue as they are.
- **A sprint** is a fixed period of work (often two weeks) with a goal. **Story points** estimate effort. **Velocity** is the average points completed per sprint. **A burndown** shows remaining work over the sprint.

**Why does this matter?** Overloaded people burn out and leave, and projects that overspend quietly become losses. Both problems are visible early if the arithmetic is done continuously, not in a spreadsheet at month five.

## The problem, in plain terms

1. **Allocations are seen one project at a time**, so nobody notices someone is at 130%.
2. **Budgets are approved informally**, and changed without a record.
3. **Labour cost needs a spreadsheet**: hours, rates, matching.
4. **Spend isn't compared with progress**, so "on budget" means "not yet over".
5. **Sprint teams track velocity separately**, and it never meets the budget.

## Capacity across every project

Allocate people to a project for **a share of their time, between two dates**. The **Capacity** page adds those allocations up **across every active project, week by week**, alongside the **remaining estimated hours** of each person's open tasks due that week.

**Weeks over 100% allocated, or with more task hours than a working week, are red.**

That's the conversation a resource meeting is meant to have, with the arithmetic already done.

## Budgets with a second pair of eyes

A project manager **proposes a budget by category**. **Someone else approves it, and only within their approval limit.** Once approved, **the budget changes only through a change request**, decided by **someone other than the person asking**, also within a limit.

**Costs are recorded by hand. Labour isn't**: it's each task's **actual hours multiplied by the assignee's rate** on that project. **Hours logged by someone without a rate are listed** rather than quietly ignored.

## Earned value, calculated

With an approved budget, earned value follows from the plan:

- **Planned value**: the budget × the share of time used;
- **Earned value**: the budget × progress;
- **Actual cost**: costs plus labour;
- **CPI** and **SPI**: earned value against actual cost and planned value;
- **Estimate at completion**: the budget ÷ CPI.

**A CPI of 0.8 means every pound or dollar is buying 80 pence or cents of planned work.** The estimate at completion **assumes that continues, and the page says so**.

## Sprints for the teams that work in them

Projects that run in sprints get a **backlog with story points**, **sprints with goals and dates**, **committed points recorded at the start** and **completed points at the close**. **Unfinished work goes back to the backlog.** **Velocity averages the last three sprints**, and **the burndown comes from when tasks were actually completed**.

## A worked example, start to finish

Here's Kofi's project, run through the AI Project Manager from the start.

**Month 1, week 1.** Kofi opens **Resources** and allocates people: Abena (senior back-end) 50% at £85 an hour, two front-end developers at 80% each, a designer at 60%. Each allocation has dates and a rate.

**Week 1, Wednesday.** He proposes a **budget**: labour £160,000, software £8,000, vendor (a payment specialist) £12,000. Total £180,000. The agency's delivery director, within her approval limit and not the proposer, approves it.

**Month 1, week 3.** The resource meeting opens **Capacity**. Abena's weeks from month 2 onwards are **red**: 50% here, 40% on the e-commerce integration, 40% on the support retainer, **130%**. Her open task hours for week 6 are 52 against a 37.5-hour week. The head of delivery moves the retainer to another developer and reduces the integration to 25%. Abena's weeks turn green at 75%.

**Month 3.** Abena logs hours against tasks every day; labour cost is calculated from them at £85 an hour. A contractor logs 20 hours **without a rate**; the hours are **listed** under the budget so Kofi can add the rate, rather than being left out.

**Month 3, end.** **Earned value**, calculated:

- Planned value: £180,000 × 50% of time used = **£90,000**.
- Earned value: £180,000 × 42% progress = **£75,600**.
- Actual cost: £8,500 software and vendor + £86,500 labour = **£95,000**.
- **CPI 0.80**: every pound buys 80p of planned work.
- **SPI 0.84**: behind schedule.
- **Estimate at completion: £226,000**, assuming the current efficiency continues.

**Month 3, end, Friday.** Kofi doesn't report green. He raises a **change request**: reduce scope (move the loyalty-points integration to phase 2) and add £15,000 for the payment specialist's extra days. The delivery director, not Kofi, approves it within her limit, with a reason. The client agrees to the scope change.

**Month 6.** The project finishes at £191,000 against a revised budget of £195,000. Abena is still at the agency.

## Five more real-world scenarios

### 1. A sprint team on a fixed budget

**Situation.** A product team runs two-week sprints inside a budgeted project.

**How TR handles it.** Sprints have goals, committed points at the start and completed points at the close. Velocity averages the last three sprints, and earned value still comes from progress and the budget.

### 2. Unfinished sprint work

**Situation.** Eight points aren't finished when the sprint closes.

**How TR handles it.** They go back to the backlog, and only completed points count towards velocity.

### 3. Approving your own budget increase

**Situation.** A project manager tries to approve a change request to their own budget.

**How TR handles it.** It's decided by someone other than the person asking, within a limit.

### 4. Hours with no rate

**Situation.** A new team member logs hours before their rate is set.

**How TR handles it.** Their hours are listed rather than ignored, so labour cost isn't understated.

### 5. A project ahead of schedule but over budget

**Situation.** SPI is 1.1 but CPI is 0.85.

**How TR handles it.** Both are shown. The project is moving fast, but every pound buys 85p of planned work, and the estimate at completion says what that means.

## Before and after

**Before.** A green status report, a developer at 130% across three projects nobody added up, and a £260,000 surprise in month five.

**After.** Capacity added up across every project, budgets approved by someone else, labour calculated from hours and rates, earned value every week, and a change request in month three instead of a resignation in month five.

## How to tell it's working

- **Red weeks on Capacity are resolved** in the resource meeting.
- **Every budget change has a change request** decided by someone else.
- **CPI and SPI are read weekly**, and changes are raised when they fall.
- **No hours sit without a rate.**

## Who it's for

- **Project managers** who own budgets and teams.
- **Delivery and resource managers** who balance people across projects.
- **Finance directors** who need early warning of overspend.

## How it fits with the rest of TicketResolve

This was the third phase of the **AI Project Manager**, after the gated lifecycle and calculated status, and scheduling with baselines and change control. The last phase added the **AI Project Manager assistant**, drafted plans, templates and the portfolio report.

## Mistakes to avoid

- **Allocating without dates.** Capacity is weekly; give allocations a start and end.
- **Recording labour by hand.** Labour comes from hours and rates.
- **Reading EAC as a promise.** It assumes current efficiency continues; change the efficiency and it changes.

## Do it in TicketResolve, step by step

**Where:** AI Project Manager → Resources, Capacity, Budget and Sprints (`/dashboard/projects/capacity`). **You'll need:** a Project Manager seat, approvers with limits, and hourly rates for the people on the project. **Full guides:** [People, budgets and sprints](https://www.ticketresolve.ai/docs/guide/project-manager-resources) and [Scheduling, baselines and changes](https://www.ticketresolve.ai/docs/guide/project-manager-schedule).

1. **Allocate people.** Open a project → **Resources**: choose the person, their share of time, the dates and their hourly rate.
2. **Check capacity.** **Capacity** shows everyone week by week; red weeks are over 100% allocated or have more task hours than the working week.
3. **Set the budget.** **Budget** → propose amounts by category. Someone else approves it within their limit; later increases go through a change request.
4. **Record costs.** Record software, vendor and other costs. Labour is calculated from task hours and rates.
5. **Read earned value.** CPI below 1 means the work costs more than planned; SPI below 1 means it's behind. The estimate at completion assumes the current efficiency continues.
6. **Raise a change when needed.** **Changes → Request a change** with its impact on schedule, budget and effort. Someone else decides it.
7. **Run sprints.** **Sprints** → plan a sprint, give backlog tasks points and move them in, start it, then close it with a retrospective note.

**How to check it worked:** Capacity shows no red weeks you haven't discussed, the budget shows an approver, and earned value updates as tasks progress.

The AI Project Manager is $99 per Project Manager seat a month and in the 7-day free trial.

## Frequently asked questions

**How is capacity calculated?**
Allocations across every active project, week by week, alongside remaining task hours due that week.

**Who approves a budget?**
Someone other than the project manager, within their approval limit.

**How do budgets change after approval?**
Only through a change request decided by someone other than the person asking.

**Is labour entered by hand?**
No. It's actual task hours times the assignee's rate.

**What happens to hours without a rate?**
They're listed, not ignored.

**What does a CPI of 0.8 mean?**
Every pound or dollar buys 80 pence or cents of planned work.

**How is velocity calculated?**
The average completed points over the last three sprints.

**Where does the burndown come from?**
From when tasks were actually completed.